I’d like to give you a little insight into my everyday work from time to time:

Last week, we were working at a wastewater treatment plant that runs 24/7 – shutting it down wasn’t an option. So, we had to work under voltage, officially and with full protective equipment, as a team of two.

Our task was to install a new outgoing feeder with a higher protection rating to handle more current.

First, we covered the dangerous areas with an insulation mat, then installed a larger NH fuse element, laid the stranded conductor to increase the cross-section, and finally adjusted the PVC panel.