Issue: https://github.com/BlowaterNostr/blowater/issues/97

Title: August Plan

Author: nostr:npub1dww6jgxykmkt7tqjqx985tg58dxlm7v83sa743578xa4j7zpe3hql6pdnf

- #1

We only finished fewer than 30% of the July Plan, which is due to poor planning and team member departure.

In August, we will plan more conservatively and put much fewer tasks to this month.

The actual plan will come out next week.

Comment: https://github.com/BlowaterNostr/blowater/issues/97#issuecomment-1691941050

Author: nostr:npub1dww6jgxykmkt7tqjqx985tg58dxlm7v83sa743578xa4j7zpe3hql6pdnf

#53

Reply to this note

Please Login to reply.

Discussion