"The report said the maximum price the government would pay was set too low and the project's bidders soon worked this out.
That decision meant proposals were "value managed down" or made cheaper on designs and timelines to make costs look acceptable.
"These value management changes represented risks that would eventually manifest themselves after procurement once construction commenced," it read."